Stage III
LKPPL has also taken up the implementation of another 2 x 371 MW combined cycle power plant under stage III expansion project. The statutory clearances from environment, consent for establishment and aviation are already obtained. LKPPL has called for bids to award EPC contract through ICB route. The EPC contract is signed and Notice to Proceed issued. With the infrastructure already available at site and the track record the company has, LKPPL is confident to commission the power plant in open cycle and combined cycle by 21 and 26 months respectively.
The ultimate capacity of the LANCO Kondapalli Power Plant after completion of Phase III would be around 1500 MW.
|